From February 17th to 18th, 2022, PRI auditor conducted a two-day Painting NADCAP Audit in HMC.
As AS9100 Audit being finished just in January, then with a seven-day New Year holiday, we only had limited time to prepare for this Painting NADCAP Audit. In this case, all relevant departments were fully involved and prepared for this audit, and we got very good result "2 minor findings". Even these findings were minor, but they were complex to close. Our responsible engineer and responsible cell leader have done a lot of work to analyze the root cause and impact, then immediately take corrective actions and provide evidences. These two findings were finally closed on 23rd March, 2022. From audit preparation to finding closure, it perfectly demonstrates the teamwork spirit of HMC.
Since our Painting NADCAP Audit results were very good for three years, and we closed these two findings on time, we get merit: Accreditation length 24 months.